PISD board discusses school construction, renovations

by | Apr 19, 2018 | Education

The new Southard middle school is one of two campuses being worked on to house the growth within PISD.

School construction and renovations were the topic of much discussion at a recent Princeton Independent School District board meeting.

Monday, April 16 the school board received information about construction of Southard Junior High School and Lowe Elementary School along with upcoming renovations on several campuses.

According to information provided by representatives from Pogue Construction, work on Lowe Elementary School has started and the piers are expected to be poured in approximately two weeks.

Renovations for Clark Junior High School will occur over the summer months including new flooring, work to the front entrance and office and a new bell system. The construction is budgeted at $350,000.

By Wyndi Veigel • News Editor • [email protected]

For the complete story see the April 19 edition or subscribe online.

Collin College Summer/Fall 2026 Registration 2

0 Comments

Subscribe Love

Related News

Collin College calls $600M bond election

Collin College calls $600M bond election

The Farmersville Campus is one of six identified by Collin College for future expansion. File Art Trustees of Collin College have called for a November bond election to raise $600 million for expansion including three new facilities. The board voted unanimously to...

read more
Save during sales tax holiday

Save during sales tax holiday

Texans can save money on tax-free purchases of most clothing, footwear, school supplies and backpacks — selling for less than $100 — during the Tax-Free weekend, a yearly event begun in 1999, the state comptroller’s office says.  Qualifying items can be purchased...

read more
Photos online